Public Works Department Secretary Mukesh Kumar Bansal (Center ) speaks with members of the inspection team at a field site during his two-day review of road and building works in Chhattisgarh on Saturday 21 November 2026. Photo: channel24india.com via CG/PR
Contractors on the Darima–Mainpat and Bario–Dhaurpur roads face proceedings to forfeit their bank guarantees. Mukesh Kumar Bansal also sets deadlines for the Kamleshwarpur college building and calls for closer supervision of medical college hospital works.
Raipur: Chhattisgarh Public Works Department (PWD) Secretary Mukesh Kumar Bansal has on Saturday November 21, 2026 directed officials to issue notices to contractors over inadequate road maintenance and slow construction after a two-day inspection across Jashpur, Surguja, Surajpur and Balrampur–Ramanujganj. He reviewed roads, bridges, culverts, college buildings and hospital works, asking engineers to monitor quality and ensure projects meet their deadlines.
Key Highlights
- Contractors responsible for the Darima–Mainpat and Bario–Dhaurpur roads are to receive notices on the proposed forfeiture of their bank guarantees. Bansal directed officials to blacklist them if they fail to carry out the required maintenance.
- At Kamleshwarpur, half of the college building’s ground-floor slab must be cast by 15 December 2026 and the entire slab completed by 15 January 2027.
- Bansal ordered immediate bituminous surfacing on the Bishunpur–Surajpur–Odgi road. The contractor for the separate 27-km Tara–Premnagar–Ramanujnagar–Krishnapur road committed to completing work by June 2027.
- The inspection also covered Darima airport and the 29.20-km Rajpur–Pratappur road, upgraded at a cost of more than ₹89 crore.
Bansal was accompanied during the tour by Engineer-in-Chief V.K. Bhatpahari, Ambikapur Region Chief Engineer K.P. Sant, Ambikapur Circle Superintending Engineer R.S. Tomar, and engineers and officers from the divisions concerned. The team inspected works in Jashpur, Manora, Sanna, Bagicha, Kansabel, Bagbahar, Kotba, Ludeg, Sitapur, Pathalgaon, Mainpat, Darima, Rajpur, Pratappur, Bhaiyathan and Surajpur.
Road contractors face action over maintenance lapses

Public Works Department Secretary Mukesh Kumar Bansal (centre) inspects a building under construction with members of the inspection team during his four-district tour of Chhattisgarh on Saturday 21 November 2026. Photo: channel24india.com via CG/PR
The inspection found that the contractors responsible for the Darima–Mainpat and Bario–Dhaurpur roads had failed to maintain them adequately during the contractual maintenance period. Bansal asked officials to issue notices under the applicable rules on forfeiture of the contractors’ bank guarantees and directed that the contractors be blacklisted if they fail to carry out the maintenance. On the Darima–Mainpat road, he also ordered painting of retaining walls, bridges, culverts and guard walls.
During the inspection of the Sontrai–Mainpat road, Bansal sought a revised estimate for widening a 1.20-km stretch from Kamleshwarpur police station junction to the Camp No. 2 temple to four lanes. He also directed officials to monitor road maintenance regularly and carry out repairs promptly.
College slab deadlines set, hospital contractor faces notice

Public Works Department Secretary Mukesh Kumar Bansal (centre-right) speaks with members of the inspection team and site personnel during a construction review in Chhattisgarh on Saturday 21 November 2026. Photo: channel24india.com via CG/PR
At the college building under construction in Kamleshwarpur, Bansal instructed the contractor to cast 50 per cent of the ground-floor slab by 15 December and complete the remaining portion by 15 January 2027. He asked officials to demarcate the college land, coordinate with the Collector to remove any encroachments found during that exercise, and install Tata Wiron fencing.
Bansal ordered a notice to the medical college hospital contractor over slow progress and called for an experienced engineer to be assigned to supervise quality. Under the inspection schedule he set, the sub-engineer will visit daily, the sub-divisional officer once every two days, and the Superintending Engineer and Chief Engineer every 30 days. The Executive Engineer will also monitor the work regularly.
Darima airport access road to be resurfaced

Public Works Department Secretary Mukesh Kumar Bansal (right of centre) listens to a briefing inside a building under construction, with project drawings on display, during his four-district tour of Chhattisgarh on Saturday 21 November 2026. Photo: channel24india.com via CG/PR
Bansal directed officials to resurface the road in front of Darima airport’s terminal building and submit a proposal for a boundary wall that meets Bureau of Civil Aviation Security standards. He asked them to begin cutting grass on the airport premises immediately.
At the PWD divisional office, he directed officials to clean the building and roof, clear weeds and attend to routine maintenance. He sought estimates for a boundary wall, a shed, repairs to staff quarters and drainage improvements. Officials were also asked to obtain the necessary approvals and promptly begin repairs to doors and windows.
Surajpur road surfacing to begin immediately
In Surajpur district, Bansal directed the immediate start of bituminous surfacing on the Bishunpur–Surajpur–Odgi road and asked engineers to ensure the work meets quality standards and stays on schedule.
On the 27-km Tara–Premnagar–Ramanujnagar–Krishnapur road, the contractor reported completing the wet mix macadam base on about 10 km and installing a batch-mix plant. The contractor said surfacing would begin after calibration and related work over the following three to four days, and committed to completing all contract work by June 2027.
Bansal also reviewed the construction of an additional room at the Surajpur Collector’s residence, repairs to the Surajpur auditorium and other ongoing works in the district.
₹89-crore Rajpur–Pratappur road inspected
In Balrampur–Ramanujganj, Bansal reviewed the condition and upkeep of the 29.20-km Rajpur–Pratappur road. The road was upgraded and strengthened in January 2026 under the Central Road Fund scheme at a cost of more than ₹89 crore. It is under a five-year performance guarantee.
![]()